OD Loads, the limits?

mrdairyflat, Mar 22, 9:52am
can someone advise please on the widths and rules as the load gets wider please! Looking to build a relocatable by hiab and truck cabin, hopng to get over 3200mtr in width.
Thanks

jmma, Mar 22, 10:13am
3200mtr thats huge (o:

mrdairyflat, Mar 22, 9:20pm
oh a misplaced "."3.200! as in 3 mtr 200mm

mrmann, Mar 22, 9:39pm
at 3.2 you will need a cetifed pilot

mrmann, Mar 22, 9:42pm
give Swanson tspt a ring in swanson they deal in that sort of stuff all the time i been out of it too long

big.b-lil.c, Mar 23, 12:16am
from memory at under 3.2m but over 2.5m you dont need a permit or a pilot however the tow vehicle must have flashing orange lights. the load must have side marker lights after dark and high vis placards during the day. best to make sure before you start could be a expensive mistake. nzta ph 0800 002828

mrfxit, Mar 23, 1:35am
2mtr with no pilots etc
Perhaps a set of twin half units that you can clip together on site then you could go to 4m total onsite.
You could go shorter then you intend now, but wider later

henderson_guy, Mar 23, 3:18am
You can go up to 3100mm wide with no pilot. Then you can go up to 4500mm with a Class 2 pilot, wider requires more pilots. If you are going to be using a Hiab contractor to shift it, they will no doubt have their own pilot. (P.S. I drive a Hiab for the building industry and often do over-dimension loads)

mrdairyflat, Aug 16, 5:58pm
Thanks all, not scarey at all.